Permalink Reply by Walter H Rose on January 26, 2010 at 11:48am
Permalink Reply by Alan Fetters on February 10, 2010 at 8:23am We are working on a new diesel plant with a large electric boiler for Unalakleet. a We logged on the the wind site yesterday afternoon. 6 Northwind 100's onsite, 4 online, producing nearly 400kW to the grid! At that moment probably nearly 50% penetration. Typical grid demand is 600 to 1000kW. No live data available on power quality or the grid. Of the two turbines down, one has electronic control board issues and the other a over torque issue. Noticed genaric warning messages poping up on the running turbines, guessing over torque since they where running near their peak?